Title Accepting interconnection requests seeking to interconnect to new transmission
Date Submitted 2/9/2023 1:01 PM
PRR Category A
Priority Emergency
Owner Wilson, Daune (CAISO)
Status Closed
Status End Date 5/16/2023 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 5.3 Complete Interconnection Request Requirement
RSS Subscribe
Existing Language
​See attached redline
Proposed Language
See attached redline​
Reason For Revision
The added language provides clarification for interconnection customers who are considering interconnecting to newly approved or yet to be approved transmission projects from the CAISO transmission planning process​
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Wilson, Daune (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

​Approve the BPM PRR as submitted

Identification of the authorship of comments

Action

Approve the BPM PRR as submitted

Recommendation based on original submission
Statement of apparent requirements of the BPM PRR

Priority and rank for any BPM PRR requiring a CAISO system change

Proposed effective date(s) of the BPM PRR

Made effective February 9, 2023 and is visible in the BPM Library
Other recommended actions

Click here to view the Final Decision for this PRR
Final Decision

As originally submitted as an emergency PRR
Stakeholder Comment

Will be addressed as part of a larger policy stakeholder initiative

Effective Date

2/9/2023
Action

Adopt the recommendation as originally issued

Made effective February 9 as an emergency PRR
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
SDG&E requests that CAISO considers revising the first sentence of the addition to Section 5.3 "The Point of Interconnection must be to an existing facility on the CAISO Controlled Grid or to a facility approved in the CAISO’s Transmission Plan..."  It does not seem CAISO's intent to preclude IRs from seeking to connect to a prior queue project's POI of a loop-in switchyard, which would not be considered an "existing facility".
2/23/2023 9:42 PM
Logged By - Sam Bustillos - SDG&E (San Diego Gas & Electric Company)
---------------------------------------------
The issue raised by SDG&E needs additional discussion that is more appropriate outside the emergency PRR process. The Issue will be addressed during an updoming policy comment process.
3/1/2023 6:54 PM
Responded By - Wilson, Daune (CAISO)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.