Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1464
Title Remainder of 2021 interconnection process enhancements initiative phase one changes
Date Submitted 8/25/2022 9:44 AM
PRR Category C
Priority Normal
Owner Wilson, Daune (CAISO)
Status Closed
Status End Date 11/15/2022 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 5.4.3.2 Projects on public sites and trust land, including land that is controlled or managed by any federal, state or local agency 6.2.9 Allocation Process for TP Deliverability
RSS Subscribe
Existing Language
 

​see posted BPM

Proposed Language
 

see attached​

Reason For Revision
 

​Incorporate remainder of anticipated tariff changes resulting from the 2021 Interconnection Process Enhancement Initiative Phase l changes.

Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Wilson, Daune (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

See attached, modifications made to recommendation.​

Identification of the authorship of comments

Comment received from GridBright
Action

Approve the BPM PRR as modified.

Adopt BMP as revised
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

November 30, 2023
Other recommended actions

none
Click here to view the Final Decision for this PRR
Final Decision

The following language is being added to Section 6.2.9.5 Criteria for Retaining TP Deliverability Allocation
The allocation of TP Deliverability for Generating Facilities that achieve Commercial Operation will have the associated deliverability status reflected as an attribute of the Generating Facility and will no longer be subject to the GIDAP TP Deliverability retention criteria. Generating Facilities’ deliverability is not permanent, and is subject to the requirements of the CAISO tariff and their GIA, including as described in Section 6.1.3.4 of the BPM for Reliability Requirements.
Stakeholder Comment

The change to the final decision is being made in response to a stakeholder comment

Effective Date

11/29/2022
Action

Adopt the recommendation as modified

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
Comment of Golden State Clean Energy (“GSCE”) on the GIDAP BPM revisions in PRR 1464
10/18/2022 5:16 PM
Logged By - Ian Kearney (Western Energy & Water)
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.