Proposed Revision Request Detail Help
PRR Life Cycle*****Stakeholder Meeting on Recommendation****
PRR Details
PRR #
1703
Title Interconnection process enhancements 5.0 implementation for commercial viability criteria and contact requirements for agreements
Date Submitted 8/26/2026 9:37 AM
PRR Category C
Priority Normal
Owner Jordan, Jill (CAISO)
Status Stakeholder Meeting on Recommendation
Status End Date 10/13/2026 11:59 PM
Related BPM Generator Management
BPM Section Add Section 3.8 - changes to contract requirements
Section 6.1.5 Commercial Viability Criteria
RSS Subscribe
Existing Language

​See attachment

Proposed Language

​See attachment​

Reason For Revision

​Implementation of IPE 5.0 tariff changes and clarification of requirement for contact changes in agreements.​

Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Jordan, Jill (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

​Approve as modified in the attached document​

Identification of the authorship of comments

Action

Approve the BPM PRR as modified.

Approve as modified in the attached document
Statement of apparent requirements of the BPM PRR

Priority and rank for any BPM PRR requiring a CAISO system change

n/a
Proposed effective date(s) of the BPM PRR

Other recommended actions

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Initial Comments
The attachment for this PRR proposes to delete three sentences at the end of § 6.1.5.6 that address cost responsibility for assigned Deliverability Network Upgrades (“DNUs”) for projects that are withdrawn from the interconnection queue due to a failure to meet commercial viability criteria.  The deletion of this language does not appear to be directly related to other modifications proposed in the PRR or the described purpose for the PRR.  The Six Cities request that the CAISO explain the basis for the proposed deletion of the language regarding DNU cost responsibility.
9/16/2026 2:55 PM
Logged By - bblair@thompsoncoburn.com (CAISO)
---------------------------------------------
The language in this section was updated to reflect that not demonstrating CVC will result in withdrawal of the project from the interconnection queue, which makes the remaining language regarding cost responsibility adjustments for DNUs irrelevant.
9/17/2026 9:53 AM
Responded By - Jordan, Jill (CAISO)
Recommendation Comments
The attachment for this PRR proposes to delete three sentences at the end of § 6.1.5.6 that address cost responsibility for assigned Deliverability Network Upgrades (“DNUs”) for projects that are withdrawn from the interconnection queue due to a failure to meet commercial viability criteria.  The Six Cities submitted an Initial Comment requesting an explanation for the proposed deletion of the language regarding DNU cost responsibility.  Upon further consideration and review of the proposed BPM for Resource Interconnection Standards included in PRR 1695, the Six Cities suggest that, to provide additional clarity, the following language be added to the first sentence of § 6.1.5.6: “and subject to any applicable Withdrawal Penalty or forfeitures of deposits.”  As recommended by the Six Cities, § 6.1.5.6 would read:  “A project that fails to meet or maintain commercial viability criteria will be withdrawn and subject to any applicable Withdrawal Penalty or forfeitures of deposits.”
10/13/2026 3:24 PM
Logged By - bblair@thompsoncoburn.com (CAISO)
---------------------------------------------
The ISO agrees with the proposed langauge and will include it, or something similar, in the final document.
10/16/2026 12:47 PM
Responded By - Jordan, Jill (CAISO)
Attachments