Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1449
Title 2021 Interconnection process enhancements phase one implementation
Date Submitted 7/29/2022 1:33 PM
PRR Category C
Priority Normal
Owner Jordan, Jill (CAISO)
Status Closed
Status End Date 10/18/2022 11:59 PM
Related BPM Generator Management
BPM Section Section 6
RSS Subscribe
Existing Language
 

​See attached

Proposed Language
 

​See attached​

Reason For Revision
 

​Changes for 2021 Interconnection Process Enhancements (IPE) Phase 1 Implementation, and an edit to Footnote 21 regarding Partial Capacity Deliverability Status (PCDS)​ for hybrid/co-located resources (not related to 2021 IPE).

Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Jordan, Jill (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

​Recommendation based on original submission

Identification of the authorship of comments

N/A
Action

Approve the BPM PRR as submitted

Recommendation based on original submission
Statement of apparent requirements of the BPM PRR

Recommendation based on original submission
Priority and rank for any BPM PRR requiring a CAISO system change

Proposed effective date(s) of the BPM PRR

Other recommended actions

Click here to view the Final Decision for this PRR
Final Decision

Approve as submitted
Stakeholder Comment

None

Effective Date

9/27/2022
Action

Adopt the recommendation as originally issued

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments