Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1426
Title Update configuration guides to support short-long start unit definitions update initiative
Date Submitted 3/25/2022 8:23 AM
PRR Category A
Priority Normal
Owner Peacock, Bonnie (CAISO)
Status Closed
Status End Date 6/14/2022 11:59 PM
Related BPM Settlements and Billing
BPM Section The following BPM and its versions are subject to the current PRR:

CG PC RA Availability Incentive Mechanism v5.10.0a
CG PC Start-up and Minimum Load Cost v5.20.0a
RSS Subscribe
Existing Language
See BPM attached to this PRR
Proposed Language
See BPM attached to this PRR
Reason For Revision
There are inconsistencies in the use of short, medium, and long start resource definitions in the Tariff, BPMs, in the market as used for optimization, and in Settlements. This change is to align all these documents and related processes when referring to resource start definitions, and support the short-long start unit definitions update initiative.

 

Configuration guides as listed above have been updated for documentation to reflect this definition alignments. Business rules and input descriptions were updated.

 

The effective date will be Trade Date 6/1/2022.
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Peacock, Bonnie (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

​The ISO proposes no modified BPM language beyond that proposed in the BPM PRR.

Identification of the authorship of comments

No comments were received.
Action

Approve the BPM PRR as submitted

N/A
Statement of apparent requirements of the BPM PRR

This BPM PRR contains basic language changes.
Priority and rank for any BPM PRR requiring a CAISO system change

There are no system changes associated with this PRR.
Proposed effective date(s) of the BPM PRR

The ISO proposes an effective date of 6/1/2022 for the BPM revisions.
Other recommended actions

The ISO does not recommend any other actions on this BPM PRR.
Click here to view the Final Decision for this PRR
Final Decision

The ISO will adopt the BPM change as proposed in the recommendation.
Stakeholder Comment

No comments submitted.

Effective Date

6/1/2022
Action

Adopt the recommendation as originally issued

None
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments