Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1290
Title Clarifications in modifications between phase I and phase II, reliability network upgrades reimbursement, and date in interconnection request for requests in deliverability
Date Submitted 10/23/2020 11:36 AM
PRR Category A
Priority Normal
Owner Tavares, Phelim (CAISO)
Status Closed
Status End Date 1/5/2021 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 6.2.5.4, 7.4, 12.1,
RSS Subscribe
Existing Language
 
See attachment
Proposed Language
 
See attachment
Reason For Revision
 
Clarifications in modifications between Phase I and Phase II, RNU reimbursement, and date in IR for requests in deliverability
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Tavares, Phelim (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

N/A
Identification of the authorship of comments

No comments submitted.
Action

Approve the BPM PRR as submitted

N/A
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

Upon completion of the PRR process
Other recommended actions

N/A
Click here to view the Final Decision for this PRR
Final Decision

Adopt recommendation as originally issued.
Stakeholder Comment

No comments

Effective Date

12/18/2020
Action

Adopt the recommendation as originally issued

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments