Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1233
Title Updated configuration guides for CC 1001, CC 1101 and CC 3101 and created new BPM configuration guides for CC 3102 and CC 1102 with regard to settlement and invoicing impacts from Black start system restoration phase 2 initiative
Date Submitted 2/27/2020 2:56 PM
PRR Category B
Priority Normal
Owner Corona, Brenda (CAISO)
Status Closed
Status End Date 4/14/2020 11:59 PM
Related BPM Settlements and Billing
BPM Section BPM – CG CC 1001 Black Start Energy Payment
BPM – CG CC 1101 Black Start Capability Allocation
BPM – CG CC 3101 Black Start Capability Settlement
BPM – CG CC 3102 Black Start Capability Settlement
BPM – CG CC 1102 Black Start Capability Allocation
BPM for Settlement and Billing
RSS Subscribe
Existing Language
 
See BPMs attached to this PRR
Proposed Language
 
See BPMs attached to this PRR
Reason For Revision
Configuration changes for the settlement and invoicing impacts in black start system restoration phase 2 initiative business requirement’s revisions. For CAISO to secure additional black start capability, the CAISO is changing its current practice regarding procurement and compensation for black start services. Therefore, CC 3102 which will be derived from black start capability payments and contractual cost recovery payments to generator owners and allocate such payments to participating transmission owners in CC 1102 on the black start capability invoice. Also, CC 1001 will also be updated to accommodate settlement of ‘BLACK START’ exceptional dispatch types.
 
The following two charge codes that will be replaced are CC 1101 black start capability allocation and CC 3101 black start capability settlement. The CC 1001 black start energy payment was updated while CC 3102 black start capability settlement and CC 1102 black start capability allocation were newly created. CC 3102 and CC 1102 will be associated with the BLACK_START_CAP_PMT charge group and the BLACK_START_CAP parent group.
 
BPM for Settlements and Billing has also been further revised to support the implementation for black start capability invoice.
The planned production deployment date is 4/29/2020 with a 5/1/2020 effective date
 
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Corona, Brenda (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

The ISO proposes no modified BPM language beyond that proposed in the BPM PRR.
Identification of the authorship of comments

No comments were received.
Action

Approve the BPM PRR as submitted

N/A
Statement of apparent requirements of the BPM PRR

This BPM PRR contains basic language changes.
Priority and rank for any BPM PRR requiring a CAISO system change

There are system changes associated with this PRR. The system changes are planned for implementation on 4/29/2020 on a normal basis.
Proposed effective date(s) of the BPM PRR

The ISO proposes an effective date of 5/1/2020 for the BPM revisions.
Other recommended actions

The ISO does not recommend any other actions on this BPM PRR.
Click here to view the Final Decision for this PRR
Final Decision

The ISO will adopt the BPM change as proposed in the recommendation.
Stakeholder Comment

No comments submitted.

Effective Date

5/1/2020
Action

Adopt the recommendation as originally issued

CC 1101 and CC3101 effective date end 4/30/20
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments