Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1214
Title Discovery date/time for forced outages
Date Submitted 11/19/2019 4:32 PM
PRR Category A
Priority Normal
Owner Abhyankar, Kalyani (CAISO)
Status Closed
Status End Date 2/19/2020 11:59 PM
Related BPM Outage Management
BPM Section section 7.2.1
RSS Subscribe
Existing Language
 
 
See attached BPM
Proposed Language
 
 
See attached BPM
Reason For Revision
 
 
The ISO is providing additional language to capture the existing process of submission of discovery date/time for forced outages.
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Abhyankar, Kalyani (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

The ISO is reviewing PG&E's comment and will provide a response as soon as possible.
Identification of the authorship of comments

Pacific Gas & Electric Company
Action

Facilitate further open meeting discussions on the submitted BPM PRR at a subsequent stakeholder meeting

Review of comments
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

Upon completion of the PRR process.
Other recommended actions

None
Click here to view the Final Decision for this PRR
Final Decision

The ISO will adopt the BPM change as proposed in the recommendation.
Stakeholder Comment

No new comments

Effective Date

2/4/2020
Action

Adopt the recommendation as originally issued

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
PG&E appreciates the opportunity to comment on the changes introduced by PRR 1214 in the Outage Management BPM.  We only have one concern.  On page 37 of the redlined Outage BPM, it currently states in section 7.2.1:
 
o If prior notice of a forced outage is not possible.
 
 For transmission facilities, the operator must notify the ISO through the Outage Management System within 30 minutesof the outage occurring. When reporting the issue to the Outage Management System, the transmission operator must include when the outage began.
 
PG&E believes it should read as follows:
 
o If prior notice of a forced outage is not possible.
 
 For transmission facilities, the operator must notify the ISO through the Outage Management System within 30 minutes of the time of discovery. When reporting the issue to the Outage Management System, the transmission operator must include when the outage began.
 
Thank you for your consideration of this minor but very important change.
12/3/2019 1:34 PM
Logged By - David Douglass (PG&E Transmission Outage Planning)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.