Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1139
Title Updates to nature of work attributes for generation outages & outage reporting section
Date Submitted 2/13/2019 9:34 PM
PRR Category B
Priority Emergency
Owner Abhyankar, Kalyani (CAISO)
Status Closed
Status End Date 5/17/2019 11:59 PM
Related BPM Outage Management
BPM Section Section 3.4
RSS Subscribe
Existing Language
 
Please refer to  the attached BPM
Proposed Language
 
Please refer to the attached BPM
Reason For Revision
 
Updates to nature of work attributes for generation outages & Outage reporting section
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Abhyankar, Kalyani (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

CAISO approves the BPM PRR as modified
Identification of the authorship of comments

Comments submitted by PG&E and SCE.
Action

Approve the BPM PRR as modified.

NA
Statement of apparent requirements of the BPM PRR

NA
Priority and rank for any BPM PRR requiring a CAISO system change

NA
Proposed effective date(s) of the BPM PRR

04/01/2019
Other recommended actions

NA
Click here to view the Final Decision for this PRR
Final Decision

The ISO has finalized the language of the BPM.
Stakeholder Comment

The stakeholders had comments regarding the updated language that were answered in the initial comments response and the PRR call.

Effective Date

5/2/2019
Action

Adopt the recommendation as originally issued

Announcements
CAISO has received written communication dated 4/17/2020 from SCE to withdraw their appeal that states:

"In light of the ISO CCE tariff filing at FERC, SCE withdraws PRR 1139 appeal.  SCE believes that the filed tariff change adequately addresses the issues that led to the appeal and as such, there is no longer a need to continue with the appeal as we await a ruling from the FERC."
Posted On - 4/17/2020 3:20 PM
CAISO has received written communication dated 3/18/2020 from SCE that states:
"With respect to 1139, SCE asks that the CAISO defer the appeal committee meeting"
Posted On - 3/19/2020 3:42 PM
12/6/2019 - Pacific Gas & Electric Company has withdrawn their appeal on PRR 1139.
Posted On - 12/6/2019 10:00 AM
Recommendation comments have been posted to this PRR.
Posted On - 4/1/2019 10:43 AM
Impact Analysis
Impact Analysis not available.
Initial Comments
California ISO Response to Initial Stakeholder Comments
4/1/2019 4:24 PM
Logged By - Payton, Julia (CAISO)
These SCE Comments are replacing their originally submitted comments.
3/6/2019 11:40 AM
Logged By - Payton, Julia (CAISO)
3/5/2019 4:41 PM
Logged By - MichaelVolpePGE (Pacific Gas & Electric Company)
Recommendation Comments
4/16/2019 3:16 PM
Logged By - Rebecca Shelton (Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California)
4/16/2019 2:06 PM
Logged By - winichen (ISO & FERC Relations)
4/16/2019 9:32 AM
Logged By - Aditya Chauhan (SCE) (Southern California Edison)
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 2
# of Appeals Abandoned - 0
#Appeal ReasonStatusResponseAppealed ByAppealed On
1Please see attachment.ClosedAditya Chauhan (SCE) (Southern California Edison)5/17/2019
2Please see attachment for PG&E's Appeal.ClosedMark Tiemens (PG&E)5/17/2019
Attachments