Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1113
Title 2018 interconnection process enhancements deliverability changes
Date Submitted 11/29/2018 5:02 PM
PRR Category C
Priority Emergency
Owner Wright, Linda (CAISO)
Status Closed
Status End Date 2/25/2019 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 4.5 Additional Deliverability Assessment Options; and 6.2 Queue Cluster Study Process
RSS Subscribe
Existing Language
 
See attached redlined document
Proposed Language
 
See attached redlined document
Reason For Revision
 
Reflects changes filed at FERC based on the 2018 Interconnection Process Enhancement (IPE) stakeholder process items 4.1, 4.2, 4.3, and 9.2 relative to deliverability and commercial viability. Effective date of November 27, 2018 is requested to reflect the requested effective date in the FERC filing.
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Wright, Linda (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

The ISO accepts the PRR as originally submitted.
Identification of the authorship of comments

No comments submitted
Action

Approve the BPM PRR as submitted

N/A
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

Effective 11/27/18
Other recommended actions

N/A
Click here to view the Final Decision for this PRR
Final Decision

The ISO accepted the PRR recommendation as modified.
Stakeholder Comment

Phoenix Consulting

Effective Date

11/27/2018
Action

Adopt the recommendation as modified

N/A
Announcements
The California ISO has posted a revised Redlined BPM to this PRR and is extending the Recommendation
comment period to 2/6/19 to allow additional time for stakeholder comments.   Reason for changes:  the ISO
has proposed changes to the GIDAP BPM based on stakeholder comments from the previous round of
stakeholder comments due January 11, 2018.
Posted On - 1/22/2019 11:39 AM
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
Attached are comments from Phoenix Consulting.  The comments accept the CAISO's redlines and suggests other changes.The highlighted sections are those where CAISO redlines were accepted. 
12/31/2018 12:19 PM
Logged By - Susan R. Schneider (Phoenix Consulting)
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.