Proposed Revision Request Detail Help
PRR Life Cycle*Initial Comment********
PRR Details
PRR #
1715
Title Clarification on the process and timeline for validating extended day ahead market and western energy imbalance market resource sufficiency evaluations test failures and implementing any resulting surcharge corrections
Date Submitted 11/20/2026 2:11 PM
PRR Category B
Priority Normal
Owner Martin, Michael (CAISO)
Status Initial Comment
Status End Date 12/10/2026 11:59 PM
Related BPM Extended Day-Ahead Market
BPM Section Section 24.5 - EDAM and WEIM Resource Sufficiency Evaluation (RSE) Validation
RSS Subscribe
Existing Language

​This is a new section

Proposed Language

In EDAM and WEIM, surcharges may apply when an EDAM RSE test or the WEIM RSE test fails, as outlined in Tariff Sections 33.11.2 and 29.11(d). The ISO will validate for RSE failures impacted by identified issues and rerun the applicable RSE tests, as necessary, to determine any required post-publication surcharge corrections. Surcharges will be subject to corrections when the ISO determines an invalid EDAM or WEIM RSE test status resulting from data input errors, software defects, or noncompliance with applicable Tariff requirements within seven business days following the applicable trade date. Corrections identified through this process will be submitted for settlement processing consistent with the applicable settlement timeline. RSE issues identified after the seven-business-day validation window are outside this routine validation and correction process and may be addressed through dispute process.​​

Reason For Revision

This change is intended to clarify the process and timeframe for validating EDAM and WEIM RSE test failures and making any resulting surcharge corrections. Establishing a seven-business-day validation window supports timely validation and settlement processing while providing a defined process for addressing issues identified after the routine validation period.​​

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.