Title Limited Operation Study Deliverability Clarification
Date Submitted 9/29/2025 11:18 AM
PRR Category A
Priority Normal
Owner Jordan, Jill (CAISO)
Status Initial Comment
Status End Date 10/15/2025 11:59 PM
Related BPM Generator Management
BPM Section Section 8
RSS Subscribe
Existing Language
 

Attached.

Proposed Language
 

​​​ Attached.​​

Reason For Revision
​Submitted by Susan R. Schneider​, Phoenix Consulting 

​​​Clarify that projects receiving permission to operate before all upgrades are complete, pursuant to a Limited Operation Study, can provide Resource Adequacy under specific circumstances even though all of their Assigned Network Upgrades are not yet complete.

Effective date: Effective at end of PRR process.

CAISO rules usually require that all Precursor and Assigned Network Upgrades be complete before a project with a TPD Allocation receives its applicable FCDS or PCDS designation.  However, projects can interconnect and operate before completion of all their reliability-related upgrades pursuant to a Limited Operation Study. 

​This PRR is needed to clarify that such projects can receive FCDS or PCDS, as applicable, once their deliverability-related upgrades are in service, even if reliability-related upgrades are not yet complete.  If the project can operate without the incomplete upgrades, they should be able to provide full RA services.​

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Attachments