Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1636
Title Updates related to implementing the shared Network Upgrade topic from the Interconnection Process Enhancements 2023 – Track 2 stakeholder initiative
Date Submitted 8/19/2025 2:30 PM
PRR Category C
Priority Emergency
Owner Chambers, Matthew (CAISO)
Status Closed
Status End Date 10/16/2025 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 8.5, 8.11.3
RSS Subscribe
Existing Language

​See attached redline markup of the BPM for GIDAP​

Proposed Language

See attached redline markup of the BPM for GIDAP​​

Reason For Revision
This is related to Stakeholder policy Interconnection Process Enhancements (IPE) Track 2.

The effective date is 8/19/2025.

Updates related to implementing the shared Network Upgrade topic in GIDAP Section 11.3.2.6 that resulted from the Interconnection Process Enhancements 2023 – Track 2 stakeholder initiative . ​​​​

Click here to view the Final Decision for this PRR
Final Decision

The version posted in the Recommendation Comments is the final version.
Stakeholder Comment

Stakeholders may submit a PRR for additional modifications

Effective Date

8/21/2025
Action

Adopt the recommendation as modified

Announcements
Replies to initial comments are attached
Posted On - 9/23/2025 10:29 AM
Impact Analysis
Initial Comments
Comment submitted, 9/17/2025 @ 14:50, by Susan R. Schneider, Principal, Phoenix Consulting. See attached document.
Logged in by J. W-Duffney (9/18/2025 @ 06:55)
9/18/2025 6:55 AM
Logged By - Williamson-Duffney, Joseph (CAISO)
Recommendation Comments
10/7/2025 11:08 AM
Logged By - Wilson, Daune (CAISO)
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments