BPM Document Library
ViewPRR
Business Practice Manual Change Management
Page Content
Proposed Revision Request Detail
PRR Life Cycle
*
*
*
*
*
*
*
*
*
Closed
PRR Details
PRR #
1188
Title
Implenting interconnection process enhancements and funds submittal requirement change
Date Submitted
8/29/2019 4:13 PM
PRR Category
B
Priority
Normal
Owner
Strouse, Nancy (CAISO)
Status
Closed
Status End Date
11/12/2019 11:59 PM
Related BPM
Generator Management
BPM Section
6.2.1.6; 6.3; 8.1; 13.4.1
Subscribe
Existing Language
See attached redlined BPM.
Proposed Language
See attached redlined BPM.
Reason For Revision
Changes to incorporate:
Implementing Interconnection Process Enhancements (IPE) 2018
Funds Submittal Requirement
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter
Strouse, Nancy (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator
The ISO is accepting modifications to the BPM language in response to stakeholder comments.
Identification of the authorship of comments
SDG&E and Joint comments from LSA, SPower and EDF-Renewables
Action
Approve the BPM PRR as modified.
The ISO has posted revised BPM language within the PRR.
Statement of apparent requirements of the BPM PRR
N/A
Priority and rank for any BPM PRR requiring a CAISO system change
N/A
Proposed effective date(s) of the BPM PRR
Upon completion of the PRR process
Other recommended actions
N/A
Click here to view the Final Decision for this PRR
Final Decision
Comments received in the Initial Stage were accepted in there entirety.
Stakeholder Comment
SDG&E and EDF-Renewables, Large-scale Solar Association (LSA), and SPower
Effective Date
10/29/2019
Action
Adopt the recommendation as modified
N/A
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
PRR 1188 BPM_for_GeneratorManagement_V25_IPE_SDGE.docx
Please see SDG&E's recommended changes in the attachment.
9/18/2019 3:03 PM
Logged By - SDG&E Generation Interconnections (San Diego Gas & Electric Company)
Phoenix - PRR 1188 comms EDFR LSA SPower 091819.docx
Joint comments on PRR 1188 from EDF-Renewables, Large-scale Solar Association (LSA), and SPower
9/18/2019 2:57 PM
Logged By - Susan R. Schneider (Phoenix Consulting)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal
# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.