Proposed Revision Request Detail Help
PRR Life Cycle*******Final Decision**
PRR Details
PRR #
1579
Title Updating TPP Phase 3 - Process for Submitting Project Sponsor Proposals
Date Submitted 7/10/2024 3:12 PM
PRR Category A
Priority Normal
Owner Rivera, Andrew (CAISO)
Status Final Decision
Status End Date 10/15/2024 11:59 PM
Related BPM Transmission Planning Process
BPM Section 5. Transmission Planning Process Phase 3
RSS Subscribe
Existing Language
 

​See attached redline with proposed changes to section 5.3

Proposed Language
 

​See attached redline with proposed changes to section 5.3

Reason For Revision
 

Required for remaining consistent with the requirements in tariff section 24.5.6. Updates to the application deposit cost value and cost cap.

Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Rivera, Andrew (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

​Approve as submitted

Identification of the authorship of comments

N/A
Action

Approve the BPM PRR as submitted

Recommendation based on original submission
Statement of apparent requirements of the BPM PRR

See attached
Priority and rank for any BPM PRR requiring a CAISO system change

Proposed effective date(s) of the BPM PRR

Other recommended actions

Click here to view the Final Decision for this PRR
Final Decision

The ISO will adopt the change as we had originally issued.
Stakeholder Comment

No comments were provided

Effective Date

Action

Adopt the recommendation as originally issued

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments