Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1346
Title Summer Readiness 2021 as it relates to market instruments
Date Submitted 4/21/2021 3:21 PM
PRR Category C
Priority Emergency
Owner Batakji, Jamal (CAISO)
Status Closed
Status End Date 7/13/2021 11:59 PM
Related BPM Market Instruments
BPM Section Attachment B
RSS Subscribe
Existing Language
 
See attached
Proposed Language
 
See attached
Reason For Revision
 
This change is related to summer readiness initiative focus on Master File changes.
Target date is July 15, 2021 
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Batakji, Jamal (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

No modifications to the original PRR are proposed.
Identification of the authorship of comments

Comment was received, and a response was posted.
Action

Approve the BPM PRR as submitted

N/A
Statement of apparent requirements of the BPM PRR

Summer Readiness 2021 as it relates to market instruments
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

July 15, 2021
Other recommended actions

No other recommended actions on this PRR.
Click here to view the Final Decision for this PRR
Final Decision

Adopt the recommendation
Stakeholder Comment

N/A

Effective Date

7/15/2021
Action

Adopt the recommendation as originally issued

N/A
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
PRR 1346 proposes to make revisions to the BPM that first requires FERC approval, as requested in CAISO’s April 28, 2021, tariff amendment filing to revise load, export, and wheeling through priorities (Docket No. ER21-1790). The proposed language in PRR 1346 does not indicate that it will go into effect only if FERC approves the tariff changes requested by CAISO in that proceeding. CAISO may not implement a change to its BPM that significantly affects the rates, terms and conditions of service.  Any revisions to the BPM that may be warranted to elaborate on or explain detail in the tariff should only be implemented if and when FERC approves CAISO’s proposed tariff changes. Therefore, PRR 1346 is premature and should not be pursued until and unless FERC approves the revisions to CAISO’s tariff requested in ER21-1790.
5/18/2021 2:06 PM
Logged By - Marcie Martin (SRP)
---------------------------------------------
Thank you for your comment. We have added a note on the document to indicate the implementation of these changes is contingent upon FERC approval.
5/26/2021 4:04 PM
Responded By - Batakji, Jamal (CAISO)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments