Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1259
Title Detailed descriptions of network upgrades
Date Submitted 6/24/2020 12:19 PM
PRR Category C
Priority Normal
Owner Wright, Linda (CAISO)
Status Closed
Status End Date 10/20/2020 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 6.1.1.4 - 6.1.1.7
RSS Subscribe
Existing Language
 
Detailed Descriptions of Delivery Network Upgrades and Off-Peak Network Upgrades
Proposed Language
 
See attached
Reason For Revision
 
Implement the area and local off-peak network upgrades in the deliverability methodology enhancement approved by FERC.
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Wright, Linda (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

SDG&E proposed grammatical changes during the Initial Comment period that have been adopted. 
Identification of the authorship of comments

SDG&E
Action

Approve the BPM PRR as modified.

Recommendation based on the revised submission.
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

August 25, 2020
Other recommended actions

N/A
Click here to view the Final Decision for this PRR
Final Decision

No changes from recommendation.
Stakeholder Comment

N/A

Effective Date

8/26/2020
Action

Adopt the recommendation as modified

N/A
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
Hello,

SDG&E's comments and suggested edits are attached for your review.

Very respectfully,

SDG&E Generation Interconnections
7/14/2020 5:19 PM
Logged By - SDG&E Generation Interconnections (San Diego Gas & Electric Company)
---------------------------------------------
Accepted the edits.
8/26/2020 10:27 AM
Responded By - Wright, Linda (CAISO)
LSA and SEIA comments on PRR 1259.  These comments state that the proposed changes go far beyond the stated rationale of incorporating FERC approval of Off-Peak Deliverability Upgrades to include substantive changes that have not been vetted properly with stakeholders.
7/14/2020 5:31 AM
Logged By - Susan R. Schneider (Phoenix Consulting)
---------------------------------------------
See CAISO response to comments in attached matrix.
7/28/2020 8:48 AM
Responded By - Billinton, Jeffrey (CAISO)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments