FERC issued an order on May 19, 2020, effective March 3, 2020, accepting the CAISO's deliverability enhancements associated with the CPUC's changes in calculating the qualifying capacity for resource adequacy and additional changes the CAISO made to its transmission planning methodology due to the time-shift of the peak hours. This change results in the CAISO calculating off-peak deliverability status for generator interconnection requests and determining if deliverability network upgrades are required for the project. The change to the BPM for Generator Management provides the customer with the information on the steps and timing needed to transfer deliverability.