Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1251
Title Implementation of FERC Order 845 changes to the Generator Interconnection Procedures
Date Submitted 5/1/2020 1:43 PM
PRR Category C
Priority Emergency
Owner Le Vine, Debi (CAISO)
Status Closed
Status End Date 7/14/2020 11:59 PM
Related BPM Generator Management
BPM Section 6, 6.2, 6.4.7, 6.5.11, 6.6 and 14
RSS Subscribe
Existing Language
 
See attached.
Proposed Language
 
See Attached.
Reason For Revision
 
Implement changes required by FERC Order 845 including requirements for control equipment, expanding modifications allowed after the studies, adding the ability to transfer surplus interconnection service and introducing permissible technological advancements.  In addition the CAISO is clarifying the facilities reassessment process.
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Le Vine, Debi (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

Various modifications were requested to Section 6.2, 6.5.11.1, 6.6.1, 6.6.2 and 14.
Identification of the authorship of comments

San Diego Gas & Electric Company
Action

Approve the BPM PRR as modified.

All proposed changes made by SDG&E were accepted except Section 6.5.11.1 because the proposed changes were inconsistent with the FERC Order.
Statement of apparent requirements of the BPM PRR

Priority and rank for any BPM PRR requiring a CAISO system change

Proposed effective date(s) of the BPM PRR

2/20/2020
Other recommended actions

Click here to view the Final Decision for this PRR
Final Decision

Modifications were made based on suggestions by SDG&E that did not conflict with the FERC Order
Stakeholder Comment

SDG&E

Effective Date

2/20/2020
Action

Adopt the recommendation as modified

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
Hello,

SDG&E's comments are attached for your review and consideration.

Thank you,

SDG&E Generation Interconnection group
5/19/2020 4:30 PM
Logged By - SDG&E Generation Interconnections (San Diego Gas & Electric Company)
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal