Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1206
Title Updates to project name guidelines, downsizing process, and affidavits for allocation
Date Submitted 10/24/2019 1:39 PM
PRR Category B
Priority Normal
Owner Tavares, Phelim (CAISO)
Status Closed
Status End Date 1/8/2020 11:59 PM
Related BPM Generator Interconnection and Deliverability Allocation Procedures
BPM Section 5.2,6.2.6.3,6.2.9.1
RSS Subscribe
Existing Language
 
see attached redline
Proposed Language
 
see attached redline
Reason For Revision
 
 Updates to project name guidelines, downsizing process, and affidavits for allocation
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Tavares, Phelim (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

See attachment
Identification of the authorship of comments

SDG&E
Action

Approve the BPM PRR as modified.

N/A
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

December 21/22019
Other recommended actions

n/a
Click here to view the Final Decision for this PRR
Final Decision

Adopt the recommendation as modified
Stakeholder Comment

SDG&E comment

Effective Date

12/23/2019
Action

Adopt the recommendation as modified

Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
11/13/2019 9:34 AM
Logged By - SDG&E Generation Interconnections (San Diego Gas & Electric Company)
Recommendation Comments
SDGE's recommended edits are attached for your review.

Thank you.
12/6/2019 4:37 PM
Logged By - SDG&E Generation Interconnections (San Diego Gas & Electric Company)
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.