Proposed Revision Request Detail Help
PRR Life Cycle*********Closed
PRR Details
PRR #
1160
Title Meter services agreement for scheduling coordinators
Date Submitted 5/31/2019 9:56 AM
PRR Category C
Priority Normal
Owner Strouse, Nancy (CAISO)
Status Closed
Status End Date 8/20/2019 11:59 PM
Related BPM Generator Management
BPM Section 3.4
RSS Subscribe
Existing Language
 
3.4 Language did not exist before.
Please see attached Redlined BPM
Proposed Language
 
Please see attached Redlined BPM
 
3.4:  Scheduling Coordinator Metered Entities:  A Scheduling Coordinator for a Scheduling Coordinator Metered Entity must sign a Meter Service Agreement for Scheduling Coordinators (MSA SC) with the CAISO.  The Scheduling Coordinator for a Scheduling Coordinator Metered Entity is responsible for providing SQMD for Scheduling Coordinator Metered Entities it represents.  Such agreements specify that Scheduling Coordinators require their Scheduling Coordinator Metered Entities to adhere to the meter requirements of the CAISO Tariff applicable to Scheduling Coordinators for Scheduling Coordinator Metered Entities, which include those set forth in Section 6 of this BPM.  A Meter Service Agreement entered into by a Scheduling Coordinator applies to the Scheduling Coordinator only in its capacity as Scheduling Coordinator for those Scheduling Coordinator Metered Entities.  A pro forma version of the Meter Service Agreement for Scheduling Coordinators is set forth in Appendix B.7 of the CAISO Tariff and can be found on the CAISO Website at: www.caiso.com.
Reason For Revision
 
Provide instruction for Meter Services Agreement for Scheduling Coordinators
Click here to view the Recommendation Details for this PRR
BPM PRR Submitter

Strouse, Nancy (CAISO)
Modified BPM language proposed by the PBM Chnage Management Coordinator

The ISO accepts the recommendation as originally submitted.
Identification of the authorship of comments

N/A
Action

Approve the BPM PRR as submitted

Approve the BPM PRR as originally submitted. 
Statement of apparent requirements of the BPM PRR

N/A
Priority and rank for any BPM PRR requiring a CAISO system change

N/A
Proposed effective date(s) of the BPM PRR

Upon completion of the PRR process.
Other recommended actions

N/A
Click here to view the Final Decision for this PRR
Final Decision

The ISO adopts the recommendation as originally issued.
Stakeholder Comment

None.

Effective Date

8/5/2019
Action

Adopt the recommendation as originally issued

The ISO adopts the recommendation as originally issued. 
Announcements
No Announcements has been posted for this PRR.
Impact Analysis
Impact Analysis not available.
Initial Comments
No Initial Comments available for this PRR.
Recommendation Comments
No Recommendation Comments available for this PRR.
Click here to view the Appeals for this PRR
Click on the '+' icon to submit a New Appeal

# of Appeals In Progress - 0
# of Appeals Closed - 0
# of Appeals Abandoned - 0
There are no Appeals on this PRR.
Attachments